A soil sample was taken from a proposed cut area in a highway construction project and sent to a soi

A soil sample was taken from a proposed cut area in a highway construction project and sent to a soils laboratory for a compaction test, using the Standard Proctor compaction procedure. Results of the test are as follows:Maximum dry unit weight = 112.6 lb/ft^3Optimum moisture content = 15.5%The contractor, during construction of the soil embankment, achieved the following:Dry unit weight reached by field compaction = 107.1 lb/ft^3Actual water content = 16.0%Determine the percent compaction achieved by the contractor.