Problem 2 A construction project is broken down into the following 10 activities: Activity Immediate


Problem 2 A construction project is broken down into the following 10 activities: Activity Immediate Pred Weeks 6 3 A 4 C 2 E Problem 2 A construction project is broken down into the following 10 activities: Activity Immediate Pred Weeks 6 3 A 4 C 2 E 4 B,C E 3 F 7 G D D, E F,H 3 I 7 G J a. Please draw the network. b. What is the critical path? c.How many weeks will it take to complete the project? d. How much slack does each of the activities have?